Renovations Completed
The renovations were completed in 5 weeks. Just in time for the peak of the school holidays. The new rooms feature the same styling and quality of the previous renovation. The newest five rooms are fitted with a double bunk and a 32 inch digital TV, displaying Austar, analog and digital TV channels.

Renovations are complete for 5 rooms – See Premier + Bunk Rooms under Family Rooms tab…….
Renovations have started at last. A long time coming but we have started today Monday 31st May, 2010.
With Lyle from Leda Constructions in control, the first day went smoothly with 4 rooms being gutted in one day. The fifth is near done and will be clear by Tuesday morning.
This is the start of the final 8 rooms of the renovation. The first stage of 13 rooms was completed in 2006 by Lyle. The final renovation will be completed in three stages. Rooms 14 to 18 being done now and will be followed by 19 and 20 and finally room 21, the stand-alone unit.
All works should be completed by the end of July.
Week One.
All rooms demolished to bare walls and concrete floor.






At the start of week Two
Most electrical completed including air-conditioning ducting and cables.

See Renovations Pages: Reno-Week 2, Reno-Week 3, Reno-Week 4, Reno-Week 5, Reno-Week 6