Renovation begin June 2010
Renovations have started at last. A long time coming but we have started today Monday 31st May, 2010.
With Lyle from Leda Constructions in control, the first day went smoothly with 4 rooms being gutted in one day. The fifth is near done and will be clear by Tuesday morning.
This is the start of the final 8 rooms of the renovation. The first stage of 13 rooms was completed in 2006 by Lyle. The final renovation will be completed in three stages. Rooms 14 to 18 being done now and will be followed by 19 and 20 and finally room 21, the stand-alone unit.
All works should be completed by the end of July.